Applicable permits and any necessary environmental clearance completed/received |
B: 165. Obtain Environmental Clearance - NEPA, ESA, etc. |
|
07/31/2021 |
05/31/2020 |
Effective implementation management and timely contract administration |
C: 119. PSMFC - Administer the Contract |
|
07/31/2021 |
06/30/2021 |
Develop or update (out-year) prioritized Habitat Project list: upload to Pisces |
D: 114. Utilize Regional Implementation Plans for Out-Year Project Prioritization and Selection |
|
02/28/2020 |
03/31/2020 |
Klickitat Passage Research and Improvement Progress Report |
E: 184. Klickitat - Modify Lamprey Passage Structure at Klickitat Lyle Falls Fish Ladder |
|
07/31/2021 |
06/30/2021 |
Klickitat Passage Research and Improvement Progress Report |
F: 115. Klickitat - Monitor adult lamprey passage behavior at modified Klickitat LPS |
|
07/31/2021 |
06/30/2021 |
Completed Annual Report |
G: 132. Klickitat - Submit Progress Report for the period (06/01/2019) to (7/31/2021) |
|
07/31/2021 |
07/28/2021 |
Reduction of Larval/Juvenile Entrainment at Yakima River Basin Diversion Progress Report |
H: 69. Yakima River Basin Diversion FVES - Installation of Flow Velocity Enhancement System (FVES) |
|
07/31/2021 |
06/30/2021 |
Reduction of Larval/Juvenile Entrainment at Yakima River Basin Diversion Progress Report |
I: 115. Yakima River Basin Diversion FVES - Test and evaluate the effect of FVES |
|
07/31/2021 |
06/30/2021 |
Completed Annual Report |
J: 132. Yakima River Basin Diversion FVES - Submit Progress Report for the period (06/01/2019) to (7/31/2021) |
|
07/31/2021 |
07/28/2021 |
Southwest Washington Lamprey Assessment Progress Report |
K: 160. Southwest Washington - Database of Adult and Juvenile Lamprey Data |
|
01/31/2021 |
01/31/2021 |
Southwest Washington Lamprey Assessment Progress Report |
L: 115. Southwest Washington - Lamprey Data Assessment and Recommendations |
|
01/31/2021 |
01/31/2021 |
Completed Annual Report |
M: 132. Southwest Washington - Submit Progress Report for the period (06/01/2019) to (12/31/2019) |
|
07/31/2021 |
07/28/2021 |
Improving adult lamprey counts in the McKenzie River Progress Report |
N: 70. Leaburg Dam McKenzie - Video Equipment Upgrade |
|
01/31/2021 |
01/31/2021 |
Improving adult lamprey counts in the McKenzie River Progress Report |
O: 115. Leaburg Dam McKenzie - Assessing Lamprey Passage Routes at Leaburg Dam |
|
01/31/2021 |
01/31/2021 |
Completed Annual Report |
P: 132. Leaburg Dam McKenzie - Submit Progress Report for the period (06/01/2019) to (12/31/2019) |
|
07/31/2021 |
07/28/2021 |
BMPs for Evaluating Lamprey Passage at Culverts Progress Report |
Q: 115. Culvert BMPs - BMPs for Evaluating Lamprey Passage at Culverts |
|
07/31/2020 |
06/29/2020 |
Completed Annual Report |
R: 132. Culvert BMPs - Submit Progress Report for the period (06/01/2019) to (12/31/2019) |
|
06/30/2020 |
06/29/2020 |
Assessments of Lamprey Passage at Fish Hatchery Fishways and Barriers Progress Report |
S: 115. Lower Columbia Passage Evaluations - Assessments of Lamprey Passage at Fish Hatchery Fishways and Barriers |
|
07/31/2021 |
06/30/2021 |
Lower Columbia Passage Evaluation Technical Report and Recommendations |
T: 122. Lower Columbia Passage Evaluations - Technical Review and Recommendations |
|
07/31/2021 |
06/30/2021 |
Completed Annual Report |
U: 132. Lower Columbia Passage Evaluations - Submit Progress Report for the period (06/01/2019) to (7/31/2021) |
|
07/31/2021 |
07/28/2021 |
Juvenile lamprey passage in the Lower Yakima/Columbia Rivers Progress Report |
V: 115. Lower Yakima Acoustic - Juvenile lamprey passage in the Lower Yakima/Columbia Rivers |
|
07/31/2020 |
05/31/2020 |
Completed Annual Report |
W: 132. Lower Yakima Acoustic - Submit Progress Report for the period (06/01/2019) to (7/31/2021) |
|
07/31/2021 |
01/31/2021 |